Service Request or Support: N/A
Issue Addressed: When a Purchase Order (PO) has a prepayment posted and you attempt to subsequently access the PO, you receive the following error: "You cannot use the Explode BOM function because a prepayment of the purchase order has been invoiced.".
Objects Affected:
Type ID Name
Page 54 Purchase Order Subform
This release does not present a change in system usage methodology.
Resolution: Ceres was enhanced by updating the Purchase Order subform (Page 54), to disable the “Explode BOM” function and error message since the “Explode BOM” function is no longer used in Ceres 5.1.